Tranquillity July 2025 Update

Tranquillity is progressing well on Ordsall Lane, as the columns and floor slab construction is now complete up to level 8. Work on the Electric LV room, sprinkler systems and internal partitions[…]

Marketing
• 4 weeks ago

Recent Build Updates

A photo of Berkeley Square during the build phase on a hot August day

We’re pleased to report that the Berkeley Square project is progressing well and on schedule. The project is in week 69 of 139, with completion anticipated in early 2026. Construction Progress This past month has seen significant progress across several areas of the site: Internally, the ground floor partitions have been completed, and work on […]

Chris
• 1 year ago
A photo of Berkeley Square during its build phase

Welcome to our latest update on the Berkeley Square West Block Phase 1 development! We’re excited to share the progress we’ve made and provide a glimpse of what’s coming up next. Construction Progress Over the last reporting period, we have achieved several significant milestones: Looking ahead, our planned activities include: Design Progress We’ve made significant […]

Chris
• 1 year ago
A photo of Berkeley Square under construction.

We are thrilled to bring you the latest update on our Berkeley Square West Bloc development. Progress is advancing smoothly with this premier residential project. Project Milestones Recent Achievements Structural Advancements: The floor slabs and frames from the lower ground to level 6 are complete. Level 7 concrete pours 1 to 3 are finished, and […]

Chris
• 1 year ago
A photo of the Berkeley Square development

We’re excited to share the latest updates on our Berkeley Square West Bloc development. Our journey towards creating a premier living development in Manchester continues progressing smoothly.  Project Overview Recent Construction Achievements: What’s Next? Looking ahead, here’s what we plan to tackle next: Design Updates Our design team has been busy refining and updating key […]

Chris
• 1 year ago
A photo of Berkeley Square build works

We’re happy to update you on the construction progress of the West Building at Berkeley Square.  Progress The construction of the concrete frame and the upper floors have made considerable headway. It has now reached the sixth floor out of the planned eight. The concrete for each floor was meticulously poured, with seven different pours […]

Chris
• 1 year ago
A photo of the build works at Berkeley Square

The fruits of the hard work and commitment of the team are moving forward to see the building realised on Berkeley Square West Block. Key Milestones We have achieved significant structural advancements in the project by completing the concrete frame and upper floors up to level 4. Each floor’s development required meticulous execution through seven […]

Chris
• 1 year ago
A photo of the 3 towers being built at Berkeley Square (Manchester)
Berkeley Square West Block is making considerable progress, with significant milestones being reached in the construction process. 
Chris
• 2 years ago