宁静 2026年4月 更新

Tranquillity continues to make exceptional progress, now sitting twelve weeks ahead of programme. With façade works advancing rapidly, internal fit-out progressing across multiple levels,…

市场营销
• 4 月 20, 2026

Tranquillity continues to make exceptional progress, now sitting twelve weeks ahead of programme. With façade works advancing rapidly, internal fit-out progressing across multiple levels, and key milestones such as PV installation and show apartment completion achieved, the project is moving confidently towards its next phase of delivery.

发生了什么

外墙和屋顶:
Brick slip installation has progressed significantly across the north elevation, while the south elevation is now largely complete with mast climbers removed. A total of sixteen mast climbers have been stripped to date, alongside all roof scaffolding. Roof balustrade and waterproofing post bases have progressed on levels 6 and 7.

内部工程:
Internal partitions are nearing completion, with second side boarding complete throughout and tape and joint works progressing up to level 7. Apartment fit-out is advancing well across levels 4, 5, and 6, including painting, flooring, tiling, joinery, and kitchen installations. Final decoration and final fix joinery have progressed to level 3, while snagging, cleaning, and finishing works are underway on lower levels.

M&E 和调试:
Second fix M&E has progressed to levels 4 and 5, with lighting now operational. Water and electrical commissioning is complete up to level 4, supporting ongoing decoration works. Electric and water meters have been installed across all levels. Corridor ceilings are fully plasterboarded, with finishing works progressing across multiple levels.

Lifts, Energy & Key Milestones
Installation of the final lift is progressing. The PV system installation is complete, with commissioning scheduled. A fully completed show apartment is now in place, providing a clear representation of the finished product.

测试与质量:
Air testing has been carried out across 130 apartments, achieving an excellent average score of 2.88, demonstrating strong build quality and airtightness performance.

North Terrace
南阳台

近期活动

  • Continue brick slip installation, façade cleaning, and final external detailing as mast climbers are dismantled.
  • Continue corridor and stair plastering works.
  • Complete tape and joint works to apartment partitions.
  • Progress apartment fit-out and commissioning ahead of decoration.
  • Continue cleaning, silicon application, carpeting, and snagging works.
  • Commence client inspections of completed apartments.
  • Begin sound testing across apartments.
  • Commence roof terrace insulation and paving works.
  • Begin balcony installation and wider external works.
  • Remove the first hoist and commence escape stair installation.

设计与质量

  • Design coordination continues, with updated external works details and ongoing drawing reviews.
  • 建筑控制设计跟踪系统确认所有项目现已结束。
  • Planning conditions are largely discharged, with only final verification required at Phase 2 completion, including Conditions 5 (Remediation), 10 (Noise Attenuation), and 25 (Site Access and Servicing), which has now been submitted.

质量保证

  • Over 8,450 QA submissions have been recorded across both phases to date.
  • Defect reports continue to be issued and managed as required.

Independent Inspections

  • Building Control (Stroma): All previously raised items have now been closed.
  • Buildzone Warranty: Latest structural inspection completed with no issues identified.
  • EWS1 Inspection: Completed, with report issued.

Utilities Update

  • Electricity: Fully complete, with meters installed across all areas.
  • Water: Fully live, with all apartment meters installed. Landlord meter installation pending, with wayleave for external pipe progressing.
  • Telecoms: Site registered with Openreach. Internal connections between buildings will be utilised, with external duct connection pending.
  • Drainage: Foul and storm connections complete, with pump chamber commissioned. Awaiting final storm discharge agreement.

健康与安全

  • Site Workforce: Average of 135 operatives on site daily, peaking at 159 during the month.

展望未来

With façade works nearing completion and internal fit-out advancing across all levels, Berkeley Square East is entering a highly visible stage of delivery. The progression into client inspections, external works, and final finishes marks a key transition towards completion, with the project maintaining excellent momentum and quality standards throughout.

敬请期待更多更新。

请与我们联系!

更多信息 宁静的曼彻斯特请查看我们的专门页面:

宁静的曼彻斯特

欢迎直接与我们联系:

01942 931300 // sales@heatongroup.co.uk // 预约电话 // 预约看房

最新职位:
宁静 2026 年 1 月更新
2 月 9, 2026
宁静 2025 年 11 月更新
12 月 1, 2025
伯克利广场 2025 年 10 月更新
10 月 28, 2025
宁静 2025 年 10 月更新
10 月 28, 2025
联系方式

投资者入职

开始您的下一次房产投资之旅。 让我们开始吧。

自我介绍:
关于您的投资

如图