Tranquillity continues to make outstanding progress on Ordsall Lane, maintaining its position nine weeks ahead of programme. With the façade and roofing works now 99.9% watertight and internal fit-out activities advancing steadily across multiple levels, the development is moving confidently towarTranquillity continues to progress strongly into the new year and is currently nine weeks ahead of programme. With the building envelope almost fully complete and internal fit-out and commissioning advancing across multiple levels, the development is moving confidently through its next phase towards its planned completion in October 2026.d its completion phase.
发生了什么
外墙和屋顶:
The façade and roofs are now 99.9% watertight, with all SFS and boarding complete and windows installed throughout. Insulation, render, and brick slips have progressed across most areas of the façade, with four mast climbers stripped to date as completed elevations are handed over.
内部工程:
Internal partitions have progressed through levels 4 to 8. Apartment fit-out continues on levels 2 and 3, including first coat painting, flooring, wall and floor tiling, joinery, and kitchen installations. Final decoration and final fix joinery have progressed to the ground floor apartments.
M&E and Commissioning:
M&E ducting installations have advanced to levels 7 and 8, with water and sprinkler pipework reaching level 5 corridors. SVPs and cable containment to corridors are now complete. First fix M&E continues on apartments at levels 4 and 5, while second fix has progressed to level 2 with lighting live. Water and electrical commissioning has been completed to the ground floor, ahead of decoration.
电梯和服务:
The second lift installation has been completed, with the third lift now underway. Works continue to the lower ground floor and LV room. Electric meters have been installed from levels 0 to 3 and are progressing upwards in line with fit-out. Temporary heating remains in place and connected to permanent power supplies.
测试与质量:
Air testing has now been completed on forty apartments, achieving an improved average score of 3.10, demonstrating strong airtightness performance.


近期活动
- 在拆除桅杆式爬升装置的同时,进行砖块滑道安装、外墙清洁和窗台工程。
- 北立面立面完工进度。
- 继续对公寓、走廊和楼梯间进行内部隔墙和机电设备的首次修复。
- 公寓装修工作继续进行,包括最后的装饰、细木工和配件。
- 地面和一楼走廊的木板天花板。
- 在机电设备投入使用后,开始对公寓进行最后装修。
- 开始管道调试,为公寓供水。
设计与质量
- Continue brick slip installation, façade cleaning, window cills, and mast climber dismantling, with works progressing to the north elevation.
- 继续对公寓、走廊和楼梯间进行内部隔墙和机电设备的首次修复。
- Continue apartment fit-out and commissioning works ahead of decoration.
- Progress corridor ceiling boarding to upper levels.
- Commence apartment cleaning and snagging.
设计与质量
- Ongoing design coordination continues.
- Lower ground floor GA plans have been updated to reflect communal area changes.
- The Building Control design tracker confirms all items are now closed.
- Planning conditions remain discharged except for further verification required at Phase 2 completion, relating to Conditions 5 (Remediation), 10 (Noise Attenuation), and 25 (Site Access and Servicing).
- NMA 2 已正式解除。
展望未来
As façade works near completion and internal fit-out accelerates across higher levels, Tranquillity continues to move into its final delivery stages with confidence. Ongoing commissioning, decoration, and snagging activities will ensure the development remains firmly ahead of programme, maintaining momentum toward the delivery of high-quality apartments in Manchester.
敬请期待更多更新。