Published: 9 months ago

Berkeley Square July Update

Welcome to our latest update on the Berkeley Square West Block Phase 1 development! We’re excited to share the progress we’ve made and provide…

Harry Stuart
• July 31, 2024
A photo of Berkeley Square during its build phase

Welcome to our latest update on the Berkeley Square West Block Phase 1 development! We’re excited to share the progress we’ve made and provide a glimpse of what’s coming up next.

Construction Progress

Over the last reporting period, we have achieved several significant milestones:

  • Concrete Work: Completed concrete frame floor slabs and parapets.
  • Wall Masonry: Finished perimeter external wall masonry, except for the face brick up to DPC.
  • Windows and Façade: We have progressed the SFS installation up to level 4 and the windows up to level 3. Façade insulation and render base coat are ongoing, and mast climbers have been installed.
  • Roof Finishes: Laid roof finishes on part of the level 6 roof terrace and core 1 roof.
  • Internal Partitions: Commenced on the upper ground floor.
  • MEP Work: We have continued SVP/RWP installation and electrical containment, with wiring and ducting in progress. We have also installed sprinkler pipework on the lower ground floor.
  • Soffit Insulation: Completed in the lower ground floor area, except for hoist areas.
  • Power Milestone: Temporary power to be used for apartment lighting and commissioning due to connection issues.

Looking ahead, our planned activities include:

  • Continuation of SFS, Windows, and Façade Work: Ongoing installation with Mastclimber platform.
  • MEP Containment and Pipework: Further installation to risers and residential floors.
  • Internal Partitions and Firestopping: Continue partitions on the upper ground floor, followed by first fixing MEP and fire stopping before closing up ceilings.
  • Roof Finishes: Complete finishes above all cores and hot melt roof finishes to levels 6 and 7.
  • Roof Terrace Balustrade: Commence installation of balustrade posts.

A photo of Berkeley Square during its build phase

Design Progress

We’ve made significant updates to our design elements:

  • Updated partition drawings
  • Revised apartment and bathroom settings
  • Detailed façade layout
  • Internal door jamb details
  • Mechanical services fire safety layouts and panel heater layouts

A photo of Berkeley Square during its build phase

Utility Update

  • Electricity: Connection accepted from LEEP; AMEON order being processed.
  • Water: Connection in Ordsall Lane, with LEEP appointed as the asset owner.
  • Telecom: Site registered, and Open Reach is connecting ducts to their chambers.
  • Drainage: Foul connection made, with storm connections pending final agreements.

We’ve included progress photos showcasing various levels and sections of the construction site.

Stay tuned for more updates.

Speak to us!

For more information on Berkeley Square, check out our dedicated page:

Berkeley Square

Feel free to contact us directly at:

01942 931300 // sales@heatongroup.co.uk 

Latest Posts:
Tranquillity Manchester March 2025 Update
March 31, 2025
Berkeley Square March 2025 Update
March 31, 2025
Tranquillity Manchester February 2025 Update
February 26, 2025
Berkeley Square February 2025 Update
February 26, 2025
Contact:

Investor Onboarding

Begin your journey to your next property investment. Lets get started.

Introduce yourself:
About your investments:

AS SEEN IN

*avg. investment yield 7%