Berkeley Square May 2025 Update

It’s been a busy month at Berkeley Square Manchester, and progress remains firmly five weeks ahead of schedule. With more apartments completed, balconies going…

Harry Stuart
• May 30, 2025

It’s been a busy month at Berkeley Square Manchester, and progress remains firmly five weeks ahead of schedule. With more apartments completed, balconies going in, and roof terraces taking shape, the team is steadily moving towards the final stages of the build.

What’s Been Happening

  • Façade Progress: The brick slip system is now complete on several elevations, with the remaining areas catching up. As mast climbers come down, window finishing works are being completed – including cills, mastic, and Juliette balconies. Roof scaffold removal is also underway.
  • Apartments and Internal Works:
    • All internal partitions are now complete.
    • Second and final MEP fixes have reached levels 5 and 6, with commissioning underway from the ground floor up to level 4.
    • Apartment fit-outs are progressing well. Level 6 has kitchens, joinery and tiling underway, while level 5 is being final decorated.
    • Snagging is ongoing on level 2. In total, 68 apartments are now fully complete.
  • Lifts and Common Areas: All lifts are installed, with two already in beneficial use. Plastering continues across corridors, staircases, and lobbies, and stair handrails are now fitted.
  • Balconies and External Features: Balcony installation has begun, and one of the two hoists has already been removed. Roof terrace insulation and paving are also due to start soon.

A photo of Berkely Square Manchester - May 2025 - North Elevation
North Elevation

What’s Coming Up

  • Ongoing façade finishing, balcony installation, and removal of remaining mast climbers.
  • Completion of second fix MEP works and continued apartment commissioning.
  • Further joinery, flooring, and decoration on levels 5, 6, and 7.
  • Installation of the stair roof slab and finishes to stair core 1.
  • Restarting MEP works on the lower ground floor.

Design and Quality

Air testing is now complete on 79 apartments with all passing and an average result of 2.89. Acoustic tests have also continued with strong results.

Looking Ahead

Despite ongoing delays to the permanent power connection (now expected in August), Berkeley Square Manchester is progressing smoothly. With key areas taking shape inside and out, the finish line is in sight.

Stay tuned for more updates.

Speak to us!

For more information on Berkeley Square Manchester, check out our dedicated page:

Berkeley Square Manchester

Feel free to contact us directly at:

01942 931300 // sales@heatongroup.co.uk // Schedule a Call // Book a Viewing

Latest Posts:
Tranquillity Manchester May 2025 Update
May 31, 2025
Tranquillity Manchester April 2025 Update
April 24, 2025
Berkeley Square April 2025 Update
April 23, 2025
Tranquillity Manchester March 2025 Update
March 31, 2025
Contact:

Investor Onboarding

Begin your journey to your next property investment. Lets get started.

Introduce yourself:
About your investments:

AS SEEN IN

*avg. investment yield 7%