Berkeley Square Manchester October 2024 Update

We’re back with the latest progress at Berkeley Square Manchester! Now in week 75 of 139, the project remains ahead of schedule, moving steadily…

Harry Stuart
• October 30, 2024
A drone photo of Berkeley Square during the build phase

We’re back with the latest progress at Berkeley Square Manchester! Now in week 75 of 139, the project remains ahead of schedule, moving steadily toward completion.

What’s Been Happening?

  • Structure and Windows: The steel framing system (SFS) has now reached level 8, creating a solid base for everything else. We’ve also installed windows up to level 6, so the building’s character is really starting to take shape.
  • Façade and Roofing: The team has been installing insulation and base layers on the façade, using mast climbers to stay quick and efficient. At the same time, the roofs are waterproofed, and work on the core structures is nearly complete—these parts might be hidden, but they’re key to a long-lasting build.
  • Inside the Building: The internal walls from levels 0 to 4 are well underway, defining each apartment’s layout. Mechanical, electrical, and plumbing (MEP) systems are progressing up to level 7, with ducting, sprinklers, and pipework getting installed to set up the infrastructure for each unit.

A photo of one of the kitchen's at Berkeley Square

Coming Up Next

In the weeks ahead, we’ll be focusing on:

  • Façade Work: We’re expecting the last of the materials soon so that the team will kick off brick slip installations on the façade.
  • Interior Finishes: We’re making headway on levels 0 and 1 with floors, kitchens, tiles, and joinery—the things that turn a building into a home.
  • Utility Updates: While we’re still waiting on the final power connection, we’ve put temporary power solutions in place to keep everything on schedule, with permanent power anticipated by March 2025.

Design, Safety, and Quality

Our design team has updated layouts and floor plans, making the most of each apartment’s space. We’re also progressing with utilities—electricity, water, telecoms, and most of the drainage work are all on track.

Health and safety remain top of mind, and we’re pleased to report another safe month with no accidents. We’re also keeping quality high, with regular inspections and fire safety tracking to ensure everything’s up to standard.

Stay tuned for more updates.

Speak to us!

For more information on Berkeley Square Manchester, check out our dedicated page:

Berkeley Square Manchester

Feel free to contact us directly at:

01942 931300 // sales@heatongroup.co.uk // Schedule a Call

Latest Posts:
Tranquillity Manchester March 2025 Update
March 31, 2025
Berkeley Square March 2025 Update
March 31, 2025
Tranquillity Manchester February 2025 Update
February 26, 2025
Berkeley Square February 2025 Update
February 26, 2025
Contact:

Investor Onboarding

Begin your journey to your next property investment. Lets get started.

Introduce yourself:
About your investments:

AS SEEN IN

*avg. investment yield 7%