已出版: 5 天 前

伯克利广场 2025 年 4 月更新

April has seen steady progress across Berkeley Square Manchester, with the team keeping things on track and five weeks ahead of schedule. While some…

哈里-斯图尔特
• 4 月 23, 2025
A bird eye view of Berkeley Square Manchester in April 2025

April has seen steady progress across 曼彻斯特伯克利广场, with the team keeping things on track and five weeks ahead of schedule. While some external challenges have pushed back the power connection, plenty of work is being completed inside and out.

发生了什么

  • 外墙和外部工程: The brick slip system is progressing well across all elevations. As sections are finished, they’re being handed over for window cills, mastic works, and Juliette balcony installations. Mast climber removal has also begun, making way for scaffolding to come down soon.
  • 内部进展:
    • Partitions are moving ahead on levels 6 to 8.
    • MEP second and final fixes have reached level 4, with first fixes complete up to level 8.
    • Floor finishes and painting are underway on level 6, while kitchens, tiling, and joinery are progressing on level 5.
    • Level 4 apartments are being final decorated, and snagging continues on level 1. So far, 38 apartments are fully complete and ready for inspection.
  • 电梯和公用设施: All lifts are installed and commissioning has started. Water is now live, but due to off-site delays—including a surprise discovery of a redundant rail tunnel—the permanent power connection is now expected by early August.
  • 测试与合规性: Air tests for 59 apartments have all passed, maintaining a strong average of 2.72. Acoustic testing is halfway complete, with excellent feedback on build quality.

下一步行动

In May, the focus will shift to:

  • Continuing façade works and starting balcony installations.
  • Completing MEP works and commissioning across the upper levels.
  • Advancing internal fit-outs on levels 4 and 5, plus ongoing snagging.
  • Finalising lift commissioning.
  • Beginning scaffold removal and preparing for landscaping phases.

A photo of Berkely Square Manchester - April 2025 - South Terrace
South Terrace

设计与质量

Design updates include roof details, access routes, and wayfinding signage. Safety remains a priority with no major incidents, though minor audit actions are being addressed. Quality checks continue across all trades, ensuring standards remain high.

展望未来

Despite the power connection delay, Berkeley Square Manchester continues to push forward. With fit-outs progressing and balconies on the horizon, we’re heading into an exciting phase.

敬请期待更多更新。

请与我们联系!

更多信息 曼彻斯特伯克利广场请查看我们的专门页面:

曼彻斯特伯克利广场

欢迎直接与我们联系:

01942 931300 // sales@heatongroup.co.uk // 预约电话 // 预约看房

最新职位:
宁静的曼彻斯特 2025 年 4 月最新情况
4 月 24, 2025
宁静的曼彻斯特 2025 年 3 月最新情况
3 月 31, 2025
伯克利广场 2025 年 3 月更新
3 月 31, 2025
宁静的曼彻斯特 2025 年 2 月最新情况
2 月 26, 2025
联系方式

投资者入职

开始您的下一次房产投资之旅。 让我们开始吧。

自我介绍:
关于您的投资

如图

* 平均投资收益 7%