For our July update, we are once again proud to confirm that progress remains ahead of schedule. With large areas of the Façade brick…

市场营销
• 7 月 30, 2025

For our July update, we are once again proud to confirm that progress remains ahead of schedule. With large areas of the Façade brick slip system complete, some balconies installed and lift installations complete; The Heaton Group are making great strides towards the final build stages.

发生了什么

  • 外墙进展: Façade brick slip system completed in areas and mast climbers have been stripped. All other elevations of brick slips are progressing in conjunction with cleaning programs. Our window contractor has been briefed to complete cills, mastic and juiliette balustrades.
  • 公寓和内部工程:
    • 所有内部分区现已完成。
    • Second and final MEP fixes have reached levels 6 and 7, with commissioning ongoing to ground and second and third floor apartments.
    • Internal finishes of kitchens and wall/floor tiling installations are complete, with joinery progressing to the final few apartments.  
    • Level 6 apartments are being final decorated, while 68 apartments on level 2 have completed the snagging process.
  • 电梯和公共区域: All lift installations are complete and two lifts have been commissioned for beneficial use. Final commissioning to complete in due course. The corridor plaster boarding has progressed to level 8, with the staircase and lift lobby plastering making steady progress.
  • 阳台和外部特征: Roof terraces insulation and paving has commenced to the level 6 roof. The PV system has also been delivered to the roof area.

北立面

近期活动

  • Continue brick slip façade insulation/render, brick slips and window cill/mastic/balustrade completion as mast climbers are stripped.
  • Progress with balcony installation.
  • Roof terrace insulation and paving.
  • Continue with decoration to levels 6, 7 and 8. Final fix of joinery continuing and snagging of completed apartments.

设计与质量

  • Air tests carried out to 134 apartments, with all apartments passed.
  • Acoustic testing carried out, in three visits so far, equating to 50% of the requirement, all passed with the comments made that the standard is very good.

展望未来

Despite off-site delays, power on is now expected mid to end of August 2025. Temporary power is currently being used to provide apartment and corridor lighting. As we begin to install rooftop insulation and paving, completion is now in sight. Project is currently at week 118 of 139, and we look forward to sharing the final stages with you.

敬请期待更多更新。

请与我们联系!

更多信息 曼彻斯特伯克利广场请查看我们的专门页面:

曼彻斯特伯克利广场

欢迎直接与我们联系:

01942 931300 // sales@heatongroup.co.uk // 预约电话 // 预约看房

最新职位:
宁静的曼彻斯特 2025 年 5 月更新
5 月 31, 2025
伯克利广场 2025 年 5 月更新
5 月 30, 2025
宁静的曼彻斯特 2025 年 4 月最新情况
4 月 24, 2025
伯克利广场 2025 年 4 月更新
4 月 23, 2025
联系方式

投资者入职

开始您的下一次房产投资之旅。 让我们开始吧。

自我介绍:
关于您的投资

如图