We’re excited to share the latest updates on our Berkeley Square West Bloc development. Our journey towards creating a premier living development in Manchester continues progressing smoothly.
Project Overview
Recent Construction Achievements:
- Structural Milestones: The slabs and frames for the lower ground to level 5 floors are complete. We’ve also made significant progress on levels 6 and 7.
- Masonry and Walls: Internal masonry for the lower ground floor is done, and work on the perimeter external wall is ongoing, especially on the north elevation and courtyard.
- Key Installations: The attenuation tank and SFS (Structural Framing System) are in place from the lower ground to level 2 on the river elevation.
- Sprinkler and Pipework: Installation of the SVP/RWP, sprinkler pipework, and dry riser pipework has begun, alongside soffit insulation in the lower ground floor area.
What’s Next?
Looking ahead, here’s what we plan to tackle next:
- Concrete Pours: Continue with the floor slab pours for levels 6, 7, and 8.
- Masonry Work: Complete the perimeter masonry walls for the lower ground floor.
- Facade and Windows: Progress with SFS curtain wall and window installations.
- Façade Insulation: Start the façade insulation and render base coat applications.
- Mechanical and Electrical Installations: Focus on M&E containment and pipework installations in the car park risers and residential floors.
- Construction Equipment: Install mast climbers and hoists.
Design Updates
Our design team has been busy refining and updating key aspects of the project:
- Drawings and Details: Updated strip sections, roof details, and window schedule elevations.
- Structural Work: Finalised setting out drawings for roof slabs and escape stair designs.
- Facade and Landscape: Issued stoneguard brick slip façade drawings and S278 drawings to SCC Highways.
Utilities and Infrastructure
- Electricity: Points of Connection are confirmed; designs are being adjusted for the Media City location.
- Water: Connection is set in Ordsall Lane, with ongoing design.
- Telecom: The site is registered, and duct routes with Open Reach are agreed upon.
- Drainage: Final agreements for connections are being finalised with Peel.
Quality Assurance
We ensure the highest standards through regular inspections and material submittals:
- Inspections: Pre-pour checks on columns and slabs are ongoing, with no issues reported.
- Independent Reviews: Building Control and warranty provider inspections continue smoothly.
Conclusion
We’re excited about the progress at Berkeley Square and remain dedicated to delivering this project on time. Stay tuned for more updates!