Tranquillity August 2025 Update

Tranquillity continues to make strong progress on Ordsall Lane, currently eight weeks ahead of programme. With the RC frame now fully complete and key…

تسويق
• سبتمبر 9, 2025

Tranquillity continues to make strong progress on Ordsall Lane, currently eight weeks ahead of programme. With the RC frame now fully complete and key structural and internal works underway, The Heaton Group continues to push the project forward across multiple areas. The project remains on track to complete in November 2026, ahead of the original planned completion date.

ماذا حدث؟

Structural and External Works: The RC frame has been fully completed. SFS works are progressing on levels 4 to 6. Windows have been installed on levels 2 and 3. Insulation, render, and brick slips are progressing in areas once the SFS and windows were installed.

Roofing: Hot melt roof finishes are progressing across the lower roofs, with single-ply roofing finishes and insulation being installed to the high-level roofs.

Internal Works and Services: Internal partitions have progressed on levels 0, 1, and 2. M&E first fix is underway in apartments on levels 0 and 1, while works to the lower ground floor and LV room continue. M&E prefix of ducting, containment, and SVP/RWP installation has advanced to levels 1–5.

الشرفة الجنوبية

المستجدات

  • Continue SFS installation, windows, and brick slip façade works.
  • Progress M&E prefix of containment, SVP’s, ducting, and pipework.
  • Continue internal partitions and M&E first fix to apartments, corridors, and stairwells.
  • First coat painting and floor finishes.
  • Tower crane removal.

Design & Quality

  • Designer reports have been updated, including partition layouts, ground floor GA, and external works setting out drawings.
  • Planning conditions tracker remains active; all conditions have been submitted except Condition 5 (remediation pending topsoil completion), pending feedback.
  • NMA 2 submission is under consideration by SCC Planning, pending feedback.

التطلع إلى الأمام

Tranquillity continues to make strong progress, with key structural, façade, and internal works advancing. The project remains on track, steadily moving towards completion to deliver high-quality apartments to Ordsall Lane, Manchester.

ترقبوا المزيد من التحديثات.

تحدث معنا!

لمزيد من المعلومات حول هدوء مانشسترقم بزيارة صفحتنا المخصصة:

هدوء مانشستر

لا تتردد في الاتصال بنا مباشرة على:

01942 931300 // المبيعات@heatongroup.co.uk // جدولة مكالمة // حجز موعد للمشاهدة

أحدث المقالات:
Berkeley Square August 2025 Update
سبتمبر 9, 2025
Tranquillity July 2025 Update
أغسطس 6, 2025
تحديث ميدان بيركلي يوليو 2025 يوليو 2025
يوليو 30، 2025
تحديث ترانكويليتي مانشستر مايو 2025
31 مايو 2025
اتصال:

دمج المستثمرين

ابدأ رحلتك نحو استثمارك العقاري القادم. دعونا نبدأ.

عرّف عن نفسك:
حول استثماراتك:

كما هو موضح في