Tranquillity August 2025 Update

Tranquillity continues to make strong progress on Ordsall Lane, currently eight weeks ahead of programme. With the RC frame now fully complete and key…

Marketing
• September 9, 2025

Tranquillity continues to make strong progress on Ordsall Lane, currently eight weeks ahead of programme. With the RC frame now fully complete and key structural and internal works underway, The Heaton Group continues to push the project forward across multiple areas. The project remains on track to complete in November 2026, ahead of the original planned completion date.

What’s Been Happening

Structural and External Works: The RC frame has been fully completed. SFS works are progressing on levels 4 to 6. Windows have been installed on levels 2 and 3. Insulation, render, and brick slips are progressing in areas once the SFS and windows were installed.

Roofing: Hot melt roof finishes are progressing across the lower roofs, with single-ply roofing finishes and insulation being installed to the high-level roofs.

Internal Works and Services: Internal partitions have progressed on levels 0, 1, and 2. M&E first fix is underway in apartments on levels 0 and 1, while works to the lower ground floor and LV room continue. M&E prefix of ducting, containment, and SVP/RWP installation has advanced to levels 1–5.

South Terrace

What’s Coming Up

  • Continue SFS installation, windows, and brick slip façade works.
  • Progress M&E prefix of containment, SVP’s, ducting, and pipework.
  • Continue internal partitions and M&E first fix to apartments, corridors, and stairwells.
  • First coat painting and floor finishes.
  • Tower crane removal.

Design & Quality

  • Designer reports have been updated, including partition layouts, ground floor GA, and external works setting out drawings.
  • Planning conditions tracker remains active; all conditions have been submitted except Condition 5 (remediation pending topsoil completion), pending feedback.
  • NMA 2 submission is under consideration by SCC Planning, pending feedback.

Looking Ahead

Tranquillity continues to make strong progress, with key structural, façade, and internal works advancing. The project remains on track, steadily moving towards completion to deliver high-quality apartments to Ordsall Lane, Manchester.

Stay tuned for more updates.

Speak to us!

For more information on Tranquillity Manchester, check out our dedicated page:

Tranquillity Manchester

Feel free to contact us directly at:

01942 931300 // sales@heatongroup.co.uk // Schedule a Call // Book a Viewing

Latest Posts:
Berkeley Square August 2025 Update
September 9, 2025
Tranquillity July 2025 Update
August 6, 2025
Berkeley Square July 2025 Update
July 30, 2025
Tranquillity Manchester May 2025 Update
May 31, 2025
Contact:

Investor Onboarding

Begin your journey to your next property investment. Lets get started.

Introduce yourself:
About your investments:

AS SEEN IN