Berkeley Square March 2025 Update

March has been another busy and productive month at Berkeley Square Manchester. Now at week 100 of 139, the project remains five weeks ahead…

Harry Stuart
• March 31, 2025
A photo South Terrace - Berkeley Square Manchester - March Update 2025

March has been another busy and productive month at Berkeley Square Manchester. Now at week 100 of 139, the project remains five weeks ahead of schedule, with key progress made across the building.

What’s Been Happening

  • Façade and External Work: Insulation, rendering, and brick slip installation are now progressing across all elevations, giving the building a polished and robust appearance.
  • Internal Fit-Out: Internal partitions are advancing on levels 6, 7, and 8, while mechanical, electrical, and plumbing (MEP) works continue. The second and final fixes are moving along on level 3, with first fixes being completed on levels 7 and 8.
    • Floor finishes and first coat painting are progressing on level 5.
    • Kitchens, wall and floor tiling, and joinery are being installed on levels 4 and 5.
    • Level 3 apartments are receiving final decorations, while snagging is ongoing for ground and level 1 apartments.
    • A total of 27 apartments are now complete and ready for inspection.
  • Lifts and Utilities: The last lift installation in core 1 is progressing well. Combined sprinkler and domestic water supply are now live in the building, using generator power and a temporary water supply. Full power is anticipated by the end of April, with the substation installation now complete.
  • Testing and Compliance: Air tests on 39 apartments have all passed, averaging a result of 2.72. Acoustic testing is now 50% complete, with feedback noting a high standard of quality.

What’s Next

Looking ahead, the focus will be on:

  • Completing façade works, including brick slip installation.
  • Finishing MEP first fix to level 8 and progressing second fixes.
  • Continuing internal partitions and firestopping, especially before ceiling closures.
  • Advancing corridor boarding to level 4.
  • Completing the last lift installation and final joinery works.
  • Connecting permanent water and power supplies to enable final commissioning.

A photo of South Terrace - Berkeley Square Manchester - March Update 2025
North Elevation

Design and Quality

Updated door schedules and landscape plans have been issued, along with progress on planning conditions and responses to feedback. Quality control remains high, with over 3,100 inspections recorded, ensuring all aspects meet rigorous standards.

Moving Forward

With final fixes and utility connections on the horizon, Berkeley Square West is shaping up well. Stay tuned for more updates!

Stay tuned for more updates.

Speak to us!

For more information on Berkeley Square Manchester, check out our dedicated page:

Berkeley Square Manchester

Feel free to contact us directly at:

01942 931300 // sales@heatongroup.co.uk // Schedule a Call // Book a Viewing

Latest Posts:
Tranquillity Manchester April 2025 Update
April 24, 2025
Berkeley Square April 2025 Update
April 23, 2025
Tranquillity Manchester March 2025 Update
March 31, 2025
Tranquillity Manchester February 2025 Update
February 26, 2025
Contact:

Investor Onboarding

Begin your journey to your next property investment. Lets get started.

Introduce yourself:
About your investments:

AS SEEN IN

*avg. investment yield 7%