已出版: 1 周 前

Tranquillity July 2025 Update

Tranquillity is progressing well on Ordsall Lane, as the columns and floor slab construction is now complete up to level 8. Work on the…

市场营销
• 8 月 6, 2025

Tranquillity is progressing well on Ordsall Lane, as the columns and floor slab construction is now complete up to level 8. Work on the Electric LV room, sprinkler systems and internal partitions are also moving forward, ensuring that the project remains on ahead of schedule.

发生了什么

Structural Progress:

• The RC frame is ongoing.
• Columns and floor slab construction is complete, with the exception of the level 8 roof parapets.

External Works:

• Insulation, render, and brick slips have progressed to low-level areas prior to mast climber installation, which is also ongoing.
• The hot melt roof finish to roofs is progressing.
• SFS is progressing from levels 2 to 4.
• Windows have been installed on levels 2 and 3.

Façade and Windows:

• Windows to levels 2 and 3 have been installed.
• Insulation, render, and brick slips have progressed to low-level areas, with mast climber installation underway.

Internal Work and Services:

• Internal and perimeter lower ground floor masonry is complete, except where hoist loading is required.
• The Electric LV room construction is complete, with a temporary door.
• M&E prefix of containment and SVP’s/RWP’s has progressed to levels 1, 2, and 3.
• The sprinkler system has been progressed to the lower ground floor.
• Internal partitions have progressed to levels 0 and 1.

奥尔索尔路高程

近期活动

  • Complete the RC parapets.
  • Continue with SFS, window and brick slip installation
  • Continue with M & E prefix of containment/SVP’s and sprinkler installation            
  • Commence the M & E first fix to apartments and corridors/stairs.

展望未来

Progress remains strong at Tranquillity Manchester, with the RC frame set to be completed and work continuing on the SFS, window, and brick slip installation. The M&E prefix of containment and sprinkler installation is advancing, while the first fix of M&E services is set to begin in the apartments, corridors, and stairwells. The building is steadily taking form, with significant milestones being achieved across multiple areas of the site.

敬请期待更多更新。

请与我们联系!

更多信息 宁静的曼彻斯特请查看我们的专门页面:

宁静的曼彻斯特

欢迎直接与我们联系:

01942 931300 // sales@heatongroup.co.uk // 预约电话 // 预约看房

最新职位:
伯克利广场 2025 年 7 月更新
7 月 30, 2025
宁静的曼彻斯特 2025 年 5 月更新
5 月 31, 2025
伯克利广场 2025 年 5 月更新
5 月 30, 2025
宁静的曼彻斯特 2025 年 4 月最新情况
4 月 24, 2025
联系方式

投资者入职

开始您的下一次房产投资之旅。 让我们开始吧。

自我介绍:
关于您的投资

如图