已出版: 1 天 前

Tranquillity August 2025 Update

Tranquillity continues to make strong progress on Ordsall Lane, currently eight weeks ahead of programme. With the RC frame now fully complete and key…

市场营销
• 9 月 9, 2025

Tranquillity continues to make strong progress on Ordsall Lane, currently eight weeks ahead of programme. With the RC frame now fully complete and key structural and internal works underway, The Heaton Group continues to push the project forward across multiple areas. The project remains on track to complete in November 2026, ahead of the original planned completion date.

发生了什么

Structural and External Works: The RC frame has been fully completed. SFS works are progressing on levels 4 to 6. Windows have been installed on levels 2 and 3. Insulation, render, and brick slips are progressing in areas once the SFS and windows were installed.

Roofing: Hot melt roof finishes are progressing across the lower roofs, with single-ply roofing finishes and insulation being installed to the high-level roofs.

Internal Works and Services: Internal partitions have progressed on levels 0, 1, and 2. M&E first fix is underway in apartments on levels 0 and 1, while works to the lower ground floor and LV room continue. M&E prefix of ducting, containment, and SVP/RWP installation has advanced to levels 1–5.

南阳台

近期活动

  • Continue SFS installation, windows, and brick slip façade works.
  • Progress M&E prefix of containment, SVP’s, ducting, and pipework.
  • Continue internal partitions and M&E first fix to apartments, corridors, and stairwells.
  • First coat painting and floor finishes.
  • Tower crane removal.

Design & Quality

  • Designer reports have been updated, including partition layouts, ground floor GA, and external works setting out drawings.
  • Planning conditions tracker remains active; all conditions have been submitted except Condition 5 (remediation pending topsoil completion), pending feedback.
  • NMA 2 submission is under consideration by SCC Planning, pending feedback.

展望未来

Tranquillity continues to make strong progress, with key structural, façade, and internal works advancing. The project remains on track, steadily moving towards completion to deliver high-quality apartments to Ordsall Lane, Manchester.

敬请期待更多更新。

请与我们联系!

更多信息 宁静的曼彻斯特请查看我们的专门页面:

宁静的曼彻斯特

欢迎直接与我们联系:

01942 931300 // sales@heatongroup.co.uk // 预约电话 // 预约看房

最新职位:
Berkeley Square August 2025 Update
9 月 9, 2025
Tranquillity July 2025 Update
8 月 6, 2025
伯克利广场 2025 年 7 月更新
7 月 30, 2025
宁静的曼彻斯特 2025 年 5 月更新
5 月 31, 2025
联系方式

投资者入职

开始您的下一次房产投资之旅。 让我们开始吧。

自我介绍:
关于您的投资

如图