Berkeley Square continues to make excellent progress on Ordsall Lane, currently nine weeks ahead of programme. With power now live on site and major milestones across the façade, apartments, and roof terraces completed, The Heaton Group is moving steadily towards early completion. The project remains on track to meet the planned completion date of October […]
Tranquillity is progressing well on Ordsall Lane, as the columns and floor slab construction is now complete up to level 8. Work on the Electric LV room, sprinkler systems and internal partitions are also moving forward, ensuring that the project remains on ahead of schedule. What’s Been Happening Structural Progress: • The RC frame is […]
For our July update, we are once again proud to confirm that progress remains ahead of schedule. With large areas of the Façade brick slip system complete, some balconies installed and lift installations complete; The Heaton Group are making great strides towards the final build stages. What’s Been Happening What’s Coming Up Design and Quality […]