March has been another busy and productive month at Berkeley Square Manchester. Now at week 100 of 139, the project remains five weeks ahead of schedule, with key progress made across the building.
What’s Been Happening
- Façade and External Work: Insulation, rendering, and brick slip installation are now progressing across all elevations, giving the building a polished and robust appearance.
- Internal Fit-Out: Internal partitions are advancing on levels 6, 7, and 8, while mechanical, electrical, and plumbing (MEP) works continue. The second and final fixes are moving along on level 3, with first fixes being completed on levels 7 and 8.
- Floor finishes and first coat painting are progressing on level 5.
- Kitchens, wall and floor tiling, and joinery are being installed on levels 4 and 5.
- Level 3 apartments are receiving final decorations, while snagging is ongoing for ground and level 1 apartments.
- A total of 27 apartments are now complete and ready for inspection.
- Lifts and Utilities: The last lift installation in core 1 is progressing well. Combined sprinkler and domestic water supply are now live in the building, using generator power and a temporary water supply. Full power is anticipated by the end of April, with the substation installation now complete.
- Testing and Compliance: Air tests on 39 apartments have all passed, averaging a result of 2.72. Acoustic testing is now 50% complete, with feedback noting a high standard of quality.
What’s Next
Looking ahead, the focus will be on:
- Completing façade works, including brick slip installation.
- Finishing MEP first fix to level 8 and progressing second fixes.
- Continuing internal partitions and firestopping, especially before ceiling closures.
- Advancing corridor boarding to level 4.
- Completing the last lift installation and final joinery works.
- Connecting permanent water and power supplies to enable final commissioning.

Design and Quality
Updated door schedules and landscape plans have been issued, along with progress on planning conditions and responses to feedback. Quality control remains high, with over 3,100 inspections recorded, ensuring all aspects meet rigorous standards.
Moving Forward
With final fixes and utility connections on the horizon, Berkeley Square West is shaping up well. Stay tuned for more updates!
Stay tuned for more updates.
Speak to us!
For more information on Berkeley Square Manchester, check out our dedicated page:
Berkeley Square Manchester
Feel free to contact us directly at:
01942 931300 // sales@heatongroup.co.uk // Schedule a Call // Book a Viewing