Berkeley Square has reached a major milestone this month, with the development officially handed over on 15th October 2025. Building Control and Buildzone warranty compliances achieved. The project continues to reflect The Heaton Group’s commitment to delivering high-quality homes and exceptional amenities in Salford. What’s Been Happening North Elevation West Elevation Courtyard Elevation What’s Coming […]
Tranquillity continues to make exceptional progress on Ordsall Lane, remaining eight weeks ahead of programme. With the SFS and window installation now complete, and internal fit-out works well underway, the development is advancing smoothly towards its planned completion date of November 2026. The site team continues to demonstrate strong coordination and momentum across all aspects […]
Tranquillity continues to make strong progress on Ordsall Lane, currently eight weeks ahead of programme. With the RC frame now fully complete and key structural and internal works underway, The Heaton Group continues to push the project forward across multiple areas. The project remains on track to complete in November 2026, ahead of the original […]
Berkeley Square continues to make excellent progress on Ordsall Lane, currently nine weeks ahead of programme. With power now live on site and major milestones across the façade, apartments, and roof terraces completed, The Heaton Group is moving steadily towards early completion. The project remains on track to meet the planned completion date of October […]
Tranquillity is progressing well on Ordsall Lane, as the columns and floor slab construction is now complete up to level 8. Work on the Electric LV room, sprinkler systems and internal partitions are also moving forward, ensuring that the project remains on ahead of schedule. What’s Been Happening Structural Progress: • The RC frame is […]
For our July update, we are once again proud to confirm that progress remains ahead of schedule. With large areas of the Façade brick slip system complete, some balconies installed and lift installations complete; The Heaton Group are making great strides towards the final build stages. What’s Been Happening What’s Coming Up Design and Quality […]
It’s been another strong month on site at Tranquillity Manchester at Berkeley Square, with the project now six weeks ahead of schedule. As the structure rises, we’re also seeing early stages of façade work and service installations getting underway. What’s Been Happening Coming Up In June Final Word The build is flying ahead at Tranquillity […]
It’s been a busy month at Berkeley Square Manchester, and progress remains firmly five weeks ahead of schedule. With more apartments completed, balconies going in, and roof terraces taking shape, the team is steadily moving towards the final stages of the build. What’s Been Happening What’s Coming Up Design and Quality Air testing is now […]
April has been a strong month for Tranquillity Manchester at Berkeley Square, with the project now five weeks ahead of schedule. The structure is rising steadily, and we’re starting to see the first glimpses of the external finishes coming together. What’s Been Happening What’s Next As we move into April, the focus will be on: […]
The Heaton Group. Unit 9, The Gatehouse, Cotton Works, Swan Meadow Road, Wigan WN3 5BE