It’s been a busy month at Berkeley Square Manchester, and progress remains firmly five weeks ahead of schedule. With more apartments completed, balconies going in, and roof terraces taking shape, the team is steadily moving towards the final stages of the build. What’s Been Happening What’s Coming Up Design and Quality Air testing is now […]
April has been a strong month for Tranquillity Manchester at Berkeley Square, with the project now five weeks ahead of schedule. The structure is rising steadily, and we’re starting to see the first glimpses of the external finishes coming together. What’s Been Happening What’s Next As we move into April, the focus will be on: […]
April has seen steady progress across Berkeley Square Manchester, with the team keeping things on track and five weeks ahead of schedule. While some external challenges have pushed back the power connection, plenty of work is being completed inside and out. What’s Been Happening What’s Next In May, the focus will shift to: Design and […]
March has been another productive month at Tranquillity at Berkeley Square. The project is now four weeks ahead of schedule, with the structural work making great progress and utilities taking shape. What’s Been Happening What’s Next As we move into April, the focus will be on: Design and Utilities Updated door schedules and landscape plans […]
March has been another busy and productive month at Berkeley Square Manchester. Now at week 100 of 139, the project remains five weeks ahead of schedule, with key progress made across the building. What’s Been Happening What’s Next Looking ahead, the focus will be on: Design and Quality Updated door schedules and landscape plans have […]
February has been another productive month at Tranquillity at Berkeley Square, keeping the project three weeks ahead of schedule. With major structural elements coming together and groundwork progressing well, the development is steadily taking shape. What’s Been Happening What’s Next As we move into March, the focus will be on: Design and Utilities The design […]
February has been another busy month at Berkeley Square Manchester, with great progress across all areas. Now at week 96 of 139, the project remains five weeks ahead of schedule, with final fixes and testing well underway. What’s Been Happening What’s Next Looking ahead, the focus will be on: Design and Quality The design team […]
The new year has brought steady progress to Tranquillity Manchester. The project remains two weeks ahead of schedule, with key structural milestones taking shape despite some challenges from the cold weather. What’s Been Happening What’s Next The team is pushing ahead with several key areas in February: Design and Utilities The design team has issued […]
The first update of 2025 is here, and it’s been a busy start to the year at Berkeley Square Manchester. We’re still five weeks ahead of schedule, despite the winter weather trying to slow things down. Progress This Month What’s Next As we move into February, the focus will be on: Utilities and Design Off-site […]