{"id":6506,"date":"2025-03-31T10:40:28","date_gmt":"2025-03-31T09:40:28","guid":{"rendered":"https:\/\/heatongroup.co.uk\/?post_type=build-updates&#038;p=6506"},"modified":"2025-03-31T10:40:29","modified_gmt":"2025-03-31T09:40:29","slug":"berkeley-square-march-2025-update","status":"publish","type":"build-updates","link":"https:\/\/heatongroup.co.uk\/zh\/build-updates\/berkeley-square-march-2025-update\/","title":{"rendered":"Berkeley Square March 2025 Update"},"content":{"rendered":"\n<p><em>March has been another busy and productive month at <a href=\"https:\/\/heatongroup.co.uk\/developments\/berkeley-square\/\">Berkeley Square Manchester<\/a>. Now at week 100 of 139, the project remains five weeks ahead of schedule, with key progress made across the building.<\/em><\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"h-what-s-been-happening\">What&#8217;s Been Happening<\/h2>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>Fa\u00e7ade and External Work<\/strong>: Insulation, rendering, and brick slip installation are now progressing across all elevations, giving the building a polished and robust appearance.<\/li>\n\n\n\n<li><strong>Internal Fit-Out<\/strong>: Internal partitions are advancing on levels 6, 7, and 8, while mechanical, electrical, and plumbing (MEP) works continue. The second and final fixes are moving along on level 3, with first fixes being completed on levels 7 and 8.\n<ul class=\"wp-block-list\">\n<li>Floor finishes and first coat painting are progressing on level 5.<\/li>\n\n\n\n<li>Kitchens, wall and floor tiling, and joinery are being installed on levels 4 and 5.<\/li>\n\n\n\n<li>Level 3 apartments are receiving final decorations, while snagging is ongoing for ground and level 1 apartments.<\/li>\n\n\n\n<li>A total of 27 apartments are now complete and ready for inspection.<\/li>\n<\/ul>\n<\/li>\n\n\n\n<li><strong>Lifts and Utilities<\/strong>: The last lift installation in core 1 is progressing well. Combined sprinkler and domestic water supply are now live in the building, using generator power and a temporary water supply. Full power is anticipated by the end of April, with the substation installation now complete.<\/li>\n\n\n\n<li><strong>Testing and Compliance<\/strong>: Air tests on 39 apartments have all passed, averaging a result of 2.72. Acoustic testing is now 50% complete, with feedback noting a high standard of quality.<\/li>\n<\/ul>\n\n\n\n<p><\/p>\n\n\n\n<figure class=\"wp-block-embed is-type-video is-provider-youtube wp-block-embed-youtube wp-embed-aspect-16-9 wp-has-aspect-ratio\"><div class=\"wp-block-embed__wrapper\">\n<iframe title=\"March 2025 Update | Berkeley Square Manchester | The Heaton Group\" width=\"800\" height=\"450\" src=\"https:\/\/www.youtube.com\/embed\/zH9AWvNZgog?feature=oembed\" frameborder=\"0\" allow=\"accelerometer; autoplay; clipboard-write; encrypted-media; gyroscope; picture-in-picture; web-share\" referrerpolicy=\"strict-origin-when-cross-origin\" allowfullscreen><\/iframe>\n<\/div><\/figure>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"h-what-s-next\">What&#8217;s Next<\/h2>\n\n\n\n<p>Looking ahead, the focus will be on:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li>Completing fa\u00e7ade works, including brick slip installation.<\/li>\n\n\n\n<li>Finishing MEP first fix to level 8 and progressing second fixes.<\/li>\n\n\n\n<li>Continuing internal partitions and firestopping, especially before ceiling closures.<\/li>\n\n\n\n<li>Advancing corridor boarding to level 4.<\/li>\n\n\n\n<li>Completing the last lift installation and final joinery works.<\/li>\n\n\n\n<li>Connecting permanent water and power supplies to enable final commissioning.<\/li>\n<\/ul>\n\n\n\n<p><\/p>\n\n\n\n<figure class=\"wp-block-image aligncenter size-large is-resized\"><img fetchpriority=\"high\" decoding=\"async\" width=\"1024\" height=\"683\" src=\"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/North-Elevation-Berkeley-Square-Manchester-March-Update-2025-1024x683.jpg\" alt=\"A photo of South Terrace - Berkeley Square Manchester - March Update 2025\" class=\"wp-image-6509\" style=\"width:667px;height:auto\" srcset=\"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/North-Elevation-Berkeley-Square-Manchester-March-Update-2025-1024x683.jpg 1024w, https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/North-Elevation-Berkeley-Square-Manchester-March-Update-2025-300x200.jpg 300w, https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/North-Elevation-Berkeley-Square-Manchester-March-Update-2025-768x512.jpg 768w, https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/North-Elevation-Berkeley-Square-Manchester-March-Update-2025-18x12.jpg 18w, https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/North-Elevation-Berkeley-Square-Manchester-March-Update-2025.jpg 1380w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><figcaption class=\"wp-element-caption\">North Elevation <\/figcaption><\/figure>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"h-design-and-quality\">Design and Quality<\/h2>\n\n\n\n<p>Updated door schedules and landscape plans have been issued, along with progress on planning conditions and responses to feedback. Quality control remains high, with over 3,100 inspections recorded, ensuring all aspects meet rigorous standards.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\" id=\"h-moving-forward\">Moving Forward<\/h2>\n\n\n\n<p>With final fixes and utility connections on the horizon, Berkeley Square West is shaping up well. Stay tuned for more updates!<\/p>\n\n\n\n<p><strong>Stay tuned for more updates.<\/strong><\/p>\n\n\n\n<h4 class=\"wp-block-heading has-text-align-center\" id=\"h-speak-to-us\">Speak to us!<\/h4>\n\n\n\n<p class=\"has-text-align-center\">For more information on <a href=\"https:\/\/heatongroup.co.uk\/developments\/berkeley-square\/\">Berkeley Square Manchester<\/a>, check out our dedicated page:<br><br><a href=\"https:\/\/heatongroup.co.uk\/developments\/tranquillity-manchester\/\"><\/a><a href=\"https:\/\/heatongroup.co.uk\/developments\/berkeley-square\/\">Berkeley Square Manchester<\/a><\/p>\n\n\n\n<p class=\"has-text-align-center\">Feel free to contact us directly at:<\/p>\n\n\n\n<p class=\"has-text-align-center\">01942 931300&nbsp;\/\/<a href=\"mailto:sales@heatongroup.co.uk\">&nbsp;sales@heatongroup.co.uk<\/a>&nbsp;\/\/ <a href=\"https:\/\/meetings.hubspot.com\/maxine-mitchell\/schedule-call\">Schedule a Call<\/a> \/\/ <a href=\"https:\/\/meetings.hubspot.com\/robert-herring\/berkeley-square-visit\">Book a Viewing<\/a><\/p>\n","protected":false},"excerpt":{"rendered":"<p>March has been another busy and productive month at Berkeley Square Manchester. Now at week 100 of 139, the project remains five weeks ahead of schedule, with key progress made across the building. What&#8217;s Been Happening What&#8217;s Next Looking ahead, the focus will be on: Design and Quality Updated door schedules and landscape plans have [&hellip;]<\/p>\n","protected":false},"author":4,"featured_media":6507,"comment_status":"open","ping_status":"open","template":"","format":"standard","meta":{"content-type":"","footnotes":""},"class_list":["post-6506","build-updates","type-build-updates","status-publish","format-standard","has-post-thumbnail","hentry"],"yoast_head":"<!-- This site is optimized with the Yoast SEO Premium plugin v25.3.1 (Yoast SEO v25.4) - https:\/\/yoast.com\/wordpress\/plugins\/seo\/ -->\n<title>Berkeley Square March 2025 Update | The Heaton Group<\/title>\n<meta name=\"description\" content=\"Berkeley Square Manchester is 5 weeks ahead of schedule, with final fixes and utility connections progressing. Discover the latest construction updates.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/heatongroup.co.uk\/zh\/build-updates\/berkeley-square-march-2025-update\/\" \/>\n<meta property=\"og:locale\" content=\"zh_CN\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Berkeley Square March 2025 Update\" \/>\n<meta property=\"og:description\" content=\"Berkeley Square Manchester is 5 weeks ahead of schedule, with final fixes and utility connections progressing. Discover the latest construction updates.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/heatongroup.co.uk\/zh\/build-updates\/berkeley-square-march-2025-update\/\" \/>\n<meta property=\"og:site_name\" content=\"Property Development &amp; Buy to Let Property | The Heaton Group\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/theheatongroup\" \/>\n<meta property=\"article:modified_time\" content=\"2025-03-31T09:40:29+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/South-Terrace-Berkeley-Square-Manchester-March-Update-2025.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"1373\" \/>\n\t<meta property=\"og:image:height\" content=\"983\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:site\" content=\"@theheatongroup\" \/>\n<meta name=\"twitter:label1\" content=\"\u9884\u8ba1\u9605\u8bfb\u65f6\u95f4\" \/>\n\t<meta name=\"twitter:data1\" content=\"3 \u5206\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"WebPage\",\"@id\":\"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/\",\"url\":\"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/\",\"name\":\"Berkeley Square March 2025 Update | The Heaton Group\",\"isPartOf\":{\"@id\":\"https:\/\/heatongroup.co.uk\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/#primaryimage\"},\"image\":{\"@id\":\"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/South-Terrace-Berkeley-Square-Manchester-March-Update-2025.jpg\",\"datePublished\":\"2025-03-31T09:40:28+00:00\",\"dateModified\":\"2025-03-31T09:40:29+00:00\",\"description\":\"Berkeley Square Manchester is 5 weeks ahead of schedule, with final fixes and utility connections progressing. Discover the latest construction updates.\",\"breadcrumb\":{\"@id\":\"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/#breadcrumb\"},\"inLanguage\":\"zh-Hans\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"zh-Hans\",\"@id\":\"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/#primaryimage\",\"url\":\"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/South-Terrace-Berkeley-Square-Manchester-March-Update-2025.jpg\",\"contentUrl\":\"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/South-Terrace-Berkeley-Square-Manchester-March-Update-2025.jpg\",\"width\":1373,\"height\":983,\"caption\":\"A photo South Terrace - Berkeley Square Manchester - March Update 2025\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\/\/heatongroup.co.uk\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Build Updates\",\"item\":\"https:\/\/heatongroup.co.uk\/build-updates\/\"},{\"@type\":\"ListItem\",\"position\":3,\"name\":\"Berkeley Square March 2025 Update\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/heatongroup.co.uk\/#website\",\"url\":\"https:\/\/heatongroup.co.uk\/\",\"name\":\"Heaton Group\",\"description\":\"Property Development &amp; Buy to Let Property\",\"publisher\":{\"@id\":\"https:\/\/heatongroup.co.uk\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/heatongroup.co.uk\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"zh-Hans\"},{\"@type\":\"Organization\",\"@id\":\"https:\/\/heatongroup.co.uk\/#organization\",\"name\":\"The Heaton Group\",\"url\":\"https:\/\/heatongroup.co.uk\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"zh-Hans\",\"@id\":\"https:\/\/heatongroup.co.uk\/#\/schema\/logo\/image\/\",\"url\":\"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2024\/02\/Heaton_Group_House_Logo_Light.jpg\",\"contentUrl\":\"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2024\/02\/Heaton_Group_House_Logo_Light.jpg\",\"width\":716,\"height\":895,\"caption\":\"The Heaton Group\"},\"image\":{\"@id\":\"https:\/\/heatongroup.co.uk\/#\/schema\/logo\/image\/\"},\"sameAs\":[\"https:\/\/www.facebook.com\/theheatongroup\",\"https:\/\/x.com\/theheatongroup\",\"https:\/\/www.instagram.com\/theheatongroup\/\",\"https:\/\/www.tiktok.com\/@heaton.group\",\"https:\/\/www.linkedin.com\/company\/heaton-group\"]}]}<\/script>\n<!-- \/ Yoast SEO Premium plugin. -->","yoast_head_json":{"title":"Berkeley Square March 2025 Update | The Heaton Group","description":"Berkeley Square Manchester is 5 weeks ahead of schedule, with final fixes and utility connections progressing. Discover the latest construction updates.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/heatongroup.co.uk\/zh\/build-updates\/berkeley-square-march-2025-update\/","og_locale":"zh_CN","og_type":"article","og_title":"Berkeley Square March 2025 Update","og_description":"Berkeley Square Manchester is 5 weeks ahead of schedule, with final fixes and utility connections progressing. Discover the latest construction updates.","og_url":"https:\/\/heatongroup.co.uk\/zh\/build-updates\/berkeley-square-march-2025-update\/","og_site_name":"Property Development &amp; Buy to Let Property | The Heaton Group","article_publisher":"https:\/\/www.facebook.com\/theheatongroup","article_modified_time":"2025-03-31T09:40:29+00:00","og_image":[{"width":1373,"height":983,"url":"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/South-Terrace-Berkeley-Square-Manchester-March-Update-2025.jpg","type":"image\/jpeg"}],"twitter_card":"summary_large_image","twitter_site":"@theheatongroup","twitter_misc":{"\u9884\u8ba1\u9605\u8bfb\u65f6\u95f4":"3 \u5206"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"WebPage","@id":"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/","url":"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/","name":"Berkeley Square March 2025 Update | The Heaton Group","isPartOf":{"@id":"https:\/\/heatongroup.co.uk\/#website"},"primaryImageOfPage":{"@id":"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/#primaryimage"},"image":{"@id":"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/#primaryimage"},"thumbnailUrl":"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/South-Terrace-Berkeley-Square-Manchester-March-Update-2025.jpg","datePublished":"2025-03-31T09:40:28+00:00","dateModified":"2025-03-31T09:40:29+00:00","description":"Berkeley Square Manchester is 5 weeks ahead of schedule, with final fixes and utility connections progressing. Discover the latest construction updates.","breadcrumb":{"@id":"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/#breadcrumb"},"inLanguage":"zh-Hans","potentialAction":[{"@type":"ReadAction","target":["https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/"]}]},{"@type":"ImageObject","inLanguage":"zh-Hans","@id":"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/#primaryimage","url":"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/South-Terrace-Berkeley-Square-Manchester-March-Update-2025.jpg","contentUrl":"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2025\/03\/South-Terrace-Berkeley-Square-Manchester-March-Update-2025.jpg","width":1373,"height":983,"caption":"A photo South Terrace - Berkeley Square Manchester - March Update 2025"},{"@type":"BreadcrumbList","@id":"https:\/\/heatongroup.co.uk\/build-updates\/berkeley-square-march-2025-update\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/heatongroup.co.uk\/"},{"@type":"ListItem","position":2,"name":"Build Updates","item":"https:\/\/heatongroup.co.uk\/build-updates\/"},{"@type":"ListItem","position":3,"name":"Berkeley Square March 2025 Update"}]},{"@type":"WebSite","@id":"https:\/\/heatongroup.co.uk\/#website","url":"https:\/\/heatongroup.co.uk\/","name":"Heaton Group","description":"Property Development &amp; Buy to Let Property","publisher":{"@id":"https:\/\/heatongroup.co.uk\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/heatongroup.co.uk\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"zh-Hans"},{"@type":"Organization","@id":"https:\/\/heatongroup.co.uk\/#organization","name":"The Heaton Group","url":"https:\/\/heatongroup.co.uk\/","logo":{"@type":"ImageObject","inLanguage":"zh-Hans","@id":"https:\/\/heatongroup.co.uk\/#\/schema\/logo\/image\/","url":"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2024\/02\/Heaton_Group_House_Logo_Light.jpg","contentUrl":"https:\/\/heatongroup.co.uk\/wp-content\/uploads\/2024\/02\/Heaton_Group_House_Logo_Light.jpg","width":716,"height":895,"caption":"The Heaton Group"},"image":{"@id":"https:\/\/heatongroup.co.uk\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/theheatongroup","https:\/\/x.com\/theheatongroup","https:\/\/www.instagram.com\/theheatongroup\/","https:\/\/www.tiktok.com\/@heaton.group","https:\/\/www.linkedin.com\/company\/heaton-group"]}]}},"_links":{"self":[{"href":"https:\/\/heatongroup.co.uk\/zh\/wp-json\/wp\/v2\/build-updates\/6506","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/heatongroup.co.uk\/zh\/wp-json\/wp\/v2\/build-updates"}],"about":[{"href":"https:\/\/heatongroup.co.uk\/zh\/wp-json\/wp\/v2\/types\/build-updates"}],"author":[{"embeddable":true,"href":"https:\/\/heatongroup.co.uk\/zh\/wp-json\/wp\/v2\/users\/4"}],"replies":[{"embeddable":true,"href":"https:\/\/heatongroup.co.uk\/zh\/wp-json\/wp\/v2\/comments?post=6506"}],"version-history":[{"count":2,"href":"https:\/\/heatongroup.co.uk\/zh\/wp-json\/wp\/v2\/build-updates\/6506\/revisions"}],"predecessor-version":[{"id":6518,"href":"https:\/\/heatongroup.co.uk\/zh\/wp-json\/wp\/v2\/build-updates\/6506\/revisions\/6518"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/heatongroup.co.uk\/zh\/wp-json\/wp\/v2\/media\/6507"}],"wp:attachment":[{"href":"https:\/\/heatongroup.co.uk\/zh\/wp-json\/wp\/v2\/media?parent=6506"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}